The sourced, up-to-date map of Dholera for the people who set up a factory, fab or data centre here. Every figure is government-tagged and dated. Not a plot-broker site.
The zone also houses the ABCD administrative building and the Integrated Command and Control Centre.
Status
A plan target across full build-out, not a current total.
The seven manufacturing figures are DSIRDA plan job targets across full build-out; the data-centre figure is a state-wide capacity target under Gujarat's Data Centre Policy, not a job number.
Three engines, one address
Not a pitch. A build already underway.
Semiconductors, energy and trunk infrastructure are being built now, which is what makes Dholera different from a plot on a map.
Is it actually happening? Where each anchor stands.
Government sources tagged green, press amber. Targets are labelled as targets, never as done.
Tata semiconductor fabUnder construction, with commercial production guided for mid-2028.Press
Dholera International AirportNot yet open. Reported ~80% complete in July 2026 after a review by the Union Civil Aviation Minister. Officials said on 16 October 2026 it is expected to be operational by the end of 2026.Press
Ahmedabad-Dholera expresswayReported operational since 31 March 2026.Press
Semi high-speed railCCEA approved the Ahmedabad (Sarkhej)-Dholera Semi High-Speed Double Line on 13 May 2026 at Rs 20,667 crore, India's first semi high-speed line, 134 km, targeted for completion up to 2030-31, connecting Ahmedabad, the SIR, the airport and Lothal (PIB release 2260624).Govt
Dholera solar parkThe NICDC Delivery Monitoring Unit report (30.06.2026) states 300 MW of the 1,000 MW Phase-I, awarded to Tata Power, has been commissioned.Govt