What a factory gets at the plot boundary in Dholera, and what is still planned

Updated 11 November 2026. Compiled by the BuildInDholera desk from the sources listed at the end of this page.

A plant in Dholera's Activation Area is reported to connect to 100 MLD of potable water, three 66 kV substations, 115 km of underground power duct, a 20 MLD effluent plant, piped natural gas and fibre ducts. These are 2024 to 2026 official figures. Larger water supply, a 2,200 million litre raw water reservoir and a desalination plant are announced or planned in November 2026.

How this list is rankedEntries are ordered by the utility a factory needs first: water, power, effluent and waste, gas, data, roads. Each row carries one status label: reported built (stated as in place by DSIRDA, DICDL or NICDC), or planned (approved or announced, not built). The figures come from the DSIRDA Sanctioned Development Plan, the NICDC Delivery Monitoring Unit report of 30 June 2026, and a 2024 DICDL interview. Anything we could not trace to one of those is left out.

Utilities at the boundary, with status

UtilityWhat is statedStatus (Nov 2026)Source and date
Potable water100 MLD available to the Activation Area, with a 50 MLD water treatment plant, a 10 million litre master balancing reservoir and 82 km of pipelineReported builtDSIRDA Sanctioned Development Plan; NICDC DMU report, 30 June 2026
Smart water meteringSmart meters and leak detection on the potable network, non-revenue water stated under 5%Reported builtDICDL interview, 2024
Power supplyThree 66 kV substationsReported builtDSIRDA Sanctioned Development Plan
Power transmission400/220 kV lines of 70 km and 30 kmReported builtDSIRDA Sanctioned Development Plan
Underground power duct115 km of underground ductReported builtDSIRDA Sanctioned Development Plan
Sewage treatment10 MLD sewage treatment plantReported builtDSIRDA Sanctioned Development Plan
Industrial effluent20 MLD common effluent treatment plant and 81 km of recycled-water pipeline, designed for zero dischargeReported builtDSIRDA Sanctioned Development Plan
Solid waste30 TPD bio-methanation plant, incinerators and a 28 hectare integrated landfillReported builtDSIRDA Sanctioned Development Plan
Piped natural gasPiped natural gas network in the underground utility corridorsReported builtDICDL interview, 2024
Data and fibreICT and fibre ducts in the underground corridors; command centre in the ABCD buildingReported builtDICDL interview, 2024
Internal roadsAbout 72 km of internal roads, 18 to 70 metres wide, with a reserved rapid-transit corridorReported builtDICDL interview, 2024
Raw water reservoir2,200 million litre reservoir and pumping station, estimate Rs 438.74 crore, 18-month build, 5-year operationPlanned (announced 3 November 2026, no contractor named)DeshGujarat, 3 November 2026
Seawater desalination, 200 MLDDetailed project report under way, reported by DeshGujarat; no tender or operating date in our recordPlanningDeshGujarat, 18 July 2026

How to read the status column

Reported built means a government document or an official interview says the item exists. It does not mean we have measured it on site, and it does not mean the capacity is free for your plant. Capacity can be committed to earlier users, so ask the Dholera Industrial City Development Limited (DICDL) for the load it can allot to your plot.

Planned items are the ones that decide whether a larger plant can run in 2028 or 2030. An announcement is not a tender notice, and it does not mean a contractor has been chosen or that work has begun.

What a fab or data centre should ask for in writing

  • The power load in MW that DICDL will commit to your parcel, and the date it will be available at the boundary.
  • The daily water volume in MLD, and whether it is potable, recycled or desalinated.
  • The effluent limit your process may send to the common effluent plant.
  • The Town Planning Scheme and Final Plot number of the parcel, matched to its survey number.

A semiconductor fab or a data centre uses far more water and power than the Activation Area figures above were sized for. The state data centre policy and the Tata fab both depend on the larger water and power works that are still at announced or planning stage.

What changed in the last four months

On 18 July 2026 DICDL was reported to be preparing a 200 MLD seawater desalination plant. On 3 November 2026 a 2,200 million litre raw water reservoir and pumping station was reported at an estimate of Rs 438.74 crore. Both are estimates and plans. Neither has an operating date in the record.

What this list cannot tell you

This list shows utilities stated for the Activation Area. It cannot tell you the capacity left for a new user, the tariff you would pay or the date a utility reaches a parcel outside that area.

Questions people ask

What infrastructure does Dholera have for industry?

Official documents describe an Activation Area with potable water, three 66 kV substations, a common effluent plant, recycled water lines, gas and fibre ducts and about 72 km of internal roads. They are reported as built. Larger water works such as a raw water reservoir and desalination are announced or planned in November 2026.

How much water does Dholera have for a factory?

The Activation Area is reported to have 100 MLD of potable water available and a 50 MLD treatment plant. A 2,200 million litre reservoir has been announced and a 200 MLD desalination plant is in planning. The record does not state how much of the 100 MLD is already committed.

Is there power for a semiconductor fab in Dholera?

The Activation Area has three 66 kV substations and 400/220 kV lines of 70 km and 30 km. About 300 MW of solar is recorded as commissioned in the Dholera solar park in the NICDC report of 30 June 2026. The record does not state the load committed to the Tata fab, so ask DICDL for a written figure.

Who do I apply to for land and utilities in Dholera?

Industrial investors apply through DICDL, the company that builds and runs the city, which operates a single-window system. Allotment and utility connection terms are set per parcel, so request them in writing for the exact plot.

Read next

Sources

  1. DSIRDA Sanctioned Development Plan and DICDL about page (extracted July 2026)
  2. NICDC Delivery Monitoring Unit report (30 June 2026)
  3. DeshGujarat, raw water reservoir report (3 November 2026)
  4. DeshGujarat, 200 MLD desalination report (18 July 2026)