Power supply for a factory in Dholera: who supplies it and what is being built
Updated 11 November 2026. Compiled by the BuildInDholera desk from the sources listed at the end of this page.
A factory in Dholera SIR's Activation Area gets power through Torrent Power, a private licensee that, per the Dholera SIR website on 13 November 2026, has built two substations including a 400/220 kV gas-insulated one with 500 MVA of distribution capacity, scalable to 1,500 MVA. GETCO is building a second 400 kV substation for dual-source supply, and a Rs 308 crore Vataman scheme was continued on 30 December 2025.
Who does what in Dholera's power chain
| Layer | Who is named | What the record says | Date of the source |
|---|---|---|---|
| Distribution to the plot | Torrent Power | Holds the distribution licence for Dholera SIR. A 2019 trade report gave a 25 year licence and about Rs 500 crore of capital spending over five years | 1 June 2019 |
| Substations inside the region | Torrent Power | Two substations built, including a 400/220 kV gas-insulated, SCADA-enabled one. Current distribution capacity 500 MVA, scalable up to 1,500 MVA. The site also says the Activation Area makes provision for two DISCOMs | Dholera SIR website, checked 13 November 2026 |
| State transmission and dual source | GETCO (Gujarat Energy Transmission Corporation Limited) | A 400 kV substation is being developed for dual-source redundancy. DICDL's financial notes record an advance to GETCO for a transmission substation at Fedra and the network up to the Activation Area | Website 13 November 2026; notes for the year ended 31 March 2025 |
| Central grid feed | Power Grid Corporation (named for the Vataman work in the CTU letter) | A 400 kV switchyard with 2 transformers of 1,500 MVA each at Vataman, estimated at Rs 308 crore, to be done within 18 months of a CTU letter dated 2 September 2024 | 29 January 2026 |
| Scheme name | National Committee on Transmission | On 30 December 2025 it decided to continue the Vataman work under the new name Transmission System for reliable power supply to Dholera area | 29 January 2026 |
| Published tariff for a Dholera factory | Not stated in the sources opened | No tariff, connection charge or load limit for Dholera industrial consumers appears in the documents we opened | Not applicable |
Download this table (CSV). Last checked 11 November 2026. Free to quote with a link to this page.
Who sells electricity to a factory in Dholera?
Torrent Power is the licensed distributor for Dholera SIR. A trade report dated 1 June 2019 said its distribution licence would run for 25 years and that it expected to spend about Rs 500 crore in the region over five years. A later T&D India article, which carries no publication date, gives the licence as valid up to 2044 and a larger plan of Rs 1,200 crore over ten years for a peak demand of about 425 MVA. The two plans are different figures from different times and neither is a commitment to any one plant. For a tariff or connection quote, a factory has to ask Torrent Power directly, because none is published in the documents we opened.
What is the Vataman scheme?
Vataman is a place where the national grid operator is building a 765 kV substation. A letter of the Central Electricity Authority, sent to the Central Transmission Utility of India Limited (CTUIL) and published on 29 January 2026, records that the National Committee on Transmission met on 30 December 2025 and decided to separate the Vataman 400 kV switchyard from an offshore wind scheme. The work continues under the name Transmission System for reliable power supply to Dholera area, with the same implementation time-frame. The letter lists the 400 kV switchyard, two 765/400 kV transformers of 1,500 MVA each, bays and bus reactors, at an estimated Rs 308 crore.
When will the scheme be finished?
The letter gives a period, not a date: 18 months from a CTU letter dated 2 September 2024. That period ran out in March 2026. We found no commissioning notice as of 13 November 2026, so treat the work as approved and not shown as complete. Check the CTUIL and CEA pages for a completion entry.
What are GETCO and Torrent building for Dholera?
The Dholera SIR website says Torrent Power has already developed two substations, one of them a 400/220 kV gas-insulated substation with SCADA, giving a current distribution capacity of 500 MVA that can scale to 1,500 MVA. It adds that a 400 kV substation is being developed by GETCO for dual-source redundancy. DICDL's annual report for 2024-25 records an advance paid to GETCO for a transmission substation at Fedra and the network to the Activation Area, without a completion date. The undated T&D India article also names a GETCO 220/33 kV Dholera substation and a 400 kV line from Panchham, which we could not confirm in an official document.
Who is already connected?
The annual report says a US Consul General toured a Torrent power substation and ReNew's manufacturing facility on 5 November 2024, and that delegates were shown a power substation on 7 and 8 March 2025. Neither source says how many industrial consumers are connected. Our status page tracks the larger projects whose power need is public.
What a factory should ask before choosing a plot
Ask DICDL which substation will feed the plot and what load is available, ask Torrent Power for the tariff category and connection charges, and ask whether the factory needs the redundant feed that the Vataman scheme is meant to give. Green power is a separate condition for data centres, covered on our green power mandate page, and incentives for manufacturers are on the incentives page.
What this page cannot tell you
This page maps who is named in the documents we opened. It publishes no tariff, load limit or completion date, because none was stated, and it does not replace a quote from Torrent Power or a feasibility check by DICDL for a specific plot.
Questions people ask
Who supplies electricity in Dholera SIR?
Torrent Power holds the distribution licence for Dholera SIR. GETCO, the Gujarat state transmission utility, builds the high-voltage lines that feed it.
What is the Vataman scheme for Dholera?
It is a central transmission scheme named Transmission System for reliable power supply to Dholera area. It covers a 400 kV switchyard and two 1,500 MVA transformers at Vataman, estimated at Rs 308 crore, as recorded in a letter published on 29 January 2026.
Is the Vataman work complete?
No completion notice was found as of 13 November 2026. The letter allows 18 months from a 2 September 2024 CTU letter, a period that ended in March 2026.
What does industrial power cost in Dholera?
The documents we opened publish no tariff for Dholera industrial consumers. Ask Torrent Power for the tariff category that applies to the plant.
Does DICDL provide the power connection?
DICDL paid an advance to GETCO for a substation and network at Fedra, according to its 2024-25 financial notes, but the licensed distributor that sells power to consumers is Torrent Power, which the Dholera SIR website lists as a private licensee.
Read next
- Set up a unit in Dholera
- Industrial land in Dholera
- Green power mandate for data centres
- Dholera project status
- GPCB consent to establish
Sources
- Central Electricity Authority letter via CTUIL: ISTS schemes approved in the 36th NCT meeting (Transmission System for reliable power supply to Dholera area) (29 January 2026)
- Dholera SIR (DSIRDA) website: Completed Projects, Power Infrastructure (checked 13 November 2026)
- DICDL 9th Annual Report 2024-25: visit by US Consul General (page 3) and financial note 9 on the GETCO advance (page 75) (Board report signed 10 November 2025)
- T&D India: Torrent Power plans Rs 500 crore capex in Dholera region (1 June 2019)