GPCB consent to establish for a factory in Gujarat: the steps and where each is done
Updated 11 November 2026. Compiled by the BuildInDholera desk from the sources listed at the end of this page.
A new factory in Gujarat applies to the Gujarat Pollution Control Board (GPCB) for consent to establish (CTE) before building, and for consent to operate, called CCA on the GPCB site, before production. GPCB publishes a document checklist, process flow charts, a categorisation list and a fee structure. This page maps those steps, checked on 13 November 2026.
From industry category to consent to operate
| Step | What you do | Where on the GPCB site | Status in the record |
|---|---|---|---|
| 1 | Find out whether your industry is Red, Orange, Green or White, and whether it is micro, small, medium or large | GPCB Industries Categorisation page, with the CPCB categorisation and the CPCB direction dated 30 April 2020 | Documents listed on the page |
| 2 | Check siting criteria for the plot | GPCB Siting Criteria page | Page exists, contents not read for this page |
| 3 | Collect the documents for a consent application | GPCB Checklist for Applications page: PDF 'List of Documents required for Consent Application' | PDF listed, contents not reproduced here |
| 4 | Apply for consent to establish (CTE) online | GPCB online portal (GPCB XGN) and the PDF 'Process Flow CTE Application' | Process flow listed |
| 5 | Pay the consent fee for your category and size | GPCB Consent Fees page | Fee figures not printed here |
| 6 | Build the plant, then apply for consent to operate (CCA) | PDF 'Process Flow CCA Application' on the Checklist page | Process flow listed |
| 7 | Renew the consent to operate when it expires | PDF 'Process Flow Renew CCA Application' | Process flow listed |
Download this table (CSV). Last checked 11 November 2026. Free to quote with a link to this page.
What CTE and CCA mean
Consent to establish is permission to set up the plant, given before construction. Consent to operate is permission to run it, given after the plant is built. GPCB's own pages call the second one CCA, short for consent and authorisation. Pollution-control consent is a legal step under the Water Act 1974 and the Air Act 1981, which require consent from the state board before an industry is established or operated.
Why the category comes first
GPCB groups industries as Red, Orange, Green and White, and by size as micro, small, medium and large. The category and size change which consent route and fee apply. GPCB's categorisation page links the state list and the central list. Use the GPCB list for your activity, because a similar-sounding activity can sit in a different category.
Documents and the online portal
GPCB's checklist page offers a PDF titled 'List of Documents required for Consent Application' and a separate PDF on obtaining CTE where environmental clearance is also involved. Applications are made through the GPCB online system. The Gujarat single window portal is also linked from the GPCB site. The exact documents depend on the category, so open the checklist PDF for your own activity.
Where Dholera comes in
A factory built on leased land in Dholera SIR is still in Gujarat, so the state consent route applies in the same way. Whether DICDL or another body adds a separate pollution or utility approval for plots in the region is not stated in the record used for this page, so ask DICDL's land allotment team when you apply for land.
What to do in order
- Fix the exact activity and capacity of the unit.
- Look it up in the GPCB categorisation list.
- Read the siting criteria against your plot.
- Prepare the documents in the checklist PDF.
- File for CTE online, pay the fee and wait for the decision.
- Build only after CTE is granted.
- Apply for CCA before you start production.
A line only this site can say
This site's incentives and sectors pages cover what a manufacturer can claim in Dholera. Consent from GPCB is a separate step that none of those schemes replaces.
What this page cannot tell you
This page maps GPCB's published steps. It does not give fees, validity periods or timelines, and it is not legal advice on any one project.
Questions people ask
What is consent to establish in Gujarat?
Permission from the Gujarat Pollution Control Board to set up an industrial unit, taken before construction. GPCB publishes a process flow for CTE applications on its checklist page. It is separate from permission to operate.
What is CCA in GPCB?
GPCB's name for consent and authorisation, the permission to operate a unit after it is built. GPCB publishes process flows for applying for it and for renewing it.
Where do I apply for GPCB consent?
Online through the GPCB portal linked from gpcb.gujarat.gov.in. The Gujarat single window portal is also linked there. Open the process flow PDF for CTE on the checklist page first.
How do I know if my factory is red, orange or green category?
Look up your activity in the GPCB Industries Categorisation page, which lists the state categorisation and the CPCB direction dated 30 April 2020. The category affects consent and fees.
What does a GPCB consent cost?
GPCB publishes a Consent Fees page. The fee depends on category and size, and this page does not print figures because they were not read in full. Open the fee page for your own case.
Does a factory in Dholera need GPCB consent?
Dholera SIR is in Gujarat, so the state board's consent route applies in the usual way. Any extra approval required by DICDL for plots in the region is not stated in the record. Ask DICDL directly.
Read next
- Set up a unit in Dholera
- Industrial land in Dholera
- Industrial FAQ
- Incentives for manufacturers
- How to bid for DICDL tenders
Sources
- GPCB Checklist for Applications (consent documents and process flows) (checked 13 November 2026)
- GPCB Industries Categorisation (checked 13 November 2026)
- GPCB Consent Fees Structure (page listed on the GPCB site 13 November 2026)
- GPCB online application portal (linked from GPCB site 13 November 2026)